Question: In the following table, the activities with their precedence sequence and expected time ( days ) are listed for a project on which Dave Carhart's

In the following table, the activities with their precedence sequence and expected time (days) are listed for a project on which
Dave Carhart's construction company is working.
The correct activity-on-node (AON) diagram for the project is shown in
Figure 3.