Question: In the following table, the activities with their precedence sequence and expected time ( days ) are listed for a project. Activity Immediate Predecessor (
In the following table, the activities with their precedence sequence and expected timedays are listed for a project.
Activity
Immediate Predecessors
Timedays
A
minus
B
A
C
A
D
B
E
B
F
C
G
E F
H
D
I
G H
Part
a Using the activityonarrow AOA LOADING... network diagram, the activities on the critical path LOADING... are
A B E G I.
A B D H I.
A C F G I.