Question: In the following table the activities with their precedence sequence and expected time ( days ) are listed for a project: Activity Immediate Predecessors Time
In the following table the activities with their precedence sequence and expected time days are listed for a project:
Activity Immediate Predecessors Time days A B A C A D B E C F C G EF H D I G J HI
Draw an AON Diagram:
Diagram must have forward and back pass and show the notations of LS LS EF LF
a Critical paths provide letters qquad days.
b The project length is days.
pls and thank you