Question: In the following table the activities with their precedence sequence and expected time ( days ) are listed for a project: Activity Immediate Predecessors Time

In the following table the activities with their precedence sequence and expected time (days) are listed for a project:
Activity Immediate Predecessors Time (days) A -6 B A 3 C A 4 D B 2 E C 6 F C 2 G E.F 3 H D 2 I G 3 J H.I 4
Draw an AON Diagram:
Diagram must have forward and back pass and show the notations of LS, LS, EF, LF
a. Critical path(s) provide letters qquad days.
b. The project length is days.
pls and thank you