Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: 9 D Activity Immediate Predecessor(s) Time

In the following table the activities with their
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: 9 D Activity Immediate Predecessor(s) Time (days) c D E F G H - IOMO > B B c EF D G H UNUN 2 4 5 5 5 5 a) The activities on the critical path are b) The project length is days