Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:

Activity Immediate Predecessor(s) Time (days) A - 7 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7

Carl's team should be able to complete the project in how many days?