Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | minus | 55 |
| B | A | 44 |
| C | A | 66 |
| D | B | 66 |
| E | B | 44 |
| F | C | 44 |
| G | D | 66 |
| H | E, F | 99 |
Carl's team should be able to complete the project in ? days.