Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) A

In the following table the activities with their precedence sequence and expected time (days) are listed for a project:

Activity

Immediate Predecessor(s)

Time (days)

A

7

B

A

2

C

A

4

D

B

5

E

B

5

F

C

5

G

E, F

2

H

D

3

I

G, H

6

a) The activities on the critical path are

A - B - E - G - I

A - B - D - H - I

A - C - F - G - I

.

b) The project length is _____days.