Question: In the following table, the activities with their precedence sequence and expected time (days) are listed for a project. Activity Immediate Predecessor(s) Time (days) A
In the following table, the activities with their precedence sequence and expected time (days) are listed for a project.
| Activity | Immediate Predecessor(s) | Time (days) |
|
|---|---|---|---|
| A | 6 | ||
| B | A | 2 | |
| C | A | 4 | |
| D | B | 5 | |
| E | B | 5 | |
| F | C | 5 | |
| G | E, F | 2 | |
| H | D | 3 | |
| I | G, H | 7 |
Part 2
a) Using the activity-on-arrow (AOA)
LOADING...
network diagram, the activities on the critical path
LOADING...
are
Part 3
b) The project length is
enter your response here
days.