Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Jake Lowe's construction company

In the following table the activities with their
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Jake Lowe's construction company is working: Activity Predecessor(s) Time (days) 5 B A 4 6 D 00 6 E B 4 F 4 G D 6 H EF 7 Based on your network diagram from the previous question: What is the project duration? 22 42 41 25