Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Immediate Predecessor(s) Time (days) 6 Activity

In the following table the activities with their

In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Immediate Predecessor(s) Time (days) 6 Activity A B D E F G . 1 A A B B E. F D G H 4 5 5 5 2 3 5 a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-1