Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:

Activity

Immediate Predecessor(s)

Time (days)

A

7

B

A

4

C

A

6

D

B

6

E

B

4

F

C

4

G

D

6

H

E, F

7

Carl's team should be able to complete the project in _____days.

Critical path activities for Carl's project are

A-B-E-H

A-B-D-G

A-C-F-H