Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 7 | |
| B | A | 4 |
| C | A | 6 |
| D | B | 6 |
| E | B | 4 |
| F | C | 4 |
| G | D | 6 |
| H | E, F | 7 |
Carl's team should be able to complete the project in _____days.
Critical path activities for Carl's project are
A-B-E-H
A-B-D-G
A-C-F-H