Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company

 In the following table the activities with their precedence sequence and

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) 7 A 4 6 6 IOM UW B 4 C 4 D 6 E, F 7 Carl's team should be able to complete the project in days. Critical path activities for Carl's project are