Question: In the forward pass through a CPM network, the EFT for an activity is computed by: A . adding the EST to the LST B
In the forward pass through a CPM network, the
EFT for an activity is computed by:
A adding the EST to the LST
B subtracting the EST from the LST
C adding the activity time to the EST
D adding slack values to the activity time