Question: In the incomplete aggregate production plan below, if the manager decides on a level production strategy, what is the planned production level for April? Period
In the incomplete aggregate production plan below, if the manager decides on a level production strategy, what is the planned production level for April? Period Jan Feb Mar Apr Demand Forecast (Uni