Question: In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a
In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone. What should the project manager do? Consult the risk response plan. Update the resource calendar. Assign the tasks to another team member. Issue a request to the change control board (CCB)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock