Question: In the Program Evaluation Review Technique ( PERT ) , slack is the Question 1 7 options: a ) excess time available after the completion

In the Program Evaluation Review Technique (PERT), slack is the
Question 17 options:
a)
excess time available after the completion of an activity which contributes to path completion before the entire project is completed.
b)
path that has the largest amount of time associated with it.
c)
number of days an activity's duration can be reduced by crashing.
d)
uncertainty associated with time estimates.