Question: In this make to order problem, the opening backlog is 160 units. Forecast demand is shown in the following chart. Calculate the weekly production for

  1. In this make to order problem, the opening backlog is 160 units. Forecast demand is shown in the following chart. Calculate the weekly production for level production if the backlog is to be decreased to 110 units.

Period

1

2

3

4

5

6

Total

Forecast Demand

90

100

90

90

80

100

Planned Production

Projected Backlog