Question: In this make to order problem, the opening backlog is 160 units. Forecast demand is shown in the following chart. Calculate the weekly production for
- In this make to order problem, the opening backlog is 160 units. Forecast demand is shown in the following chart. Calculate the weekly production for level production if the backlog is to be decreased to 110 units.
| Period | 1 | 2 | 3 | 4 | 5 | 6 | Total | |
| Forecast Demand | 90 | 100 | 90 | 90 | 80 | 100 |
| |
| Planned Production |
|
|
|
|
|
|
| |
| Projected Backlog |
|
|
|
|
|
|
|
|