Question: IN this problem, I have a design that implements cuts and fills. The Black line is the design surface and the orange line is the

IN this problem, I have a design that implements cuts and fills. The Black line is the design surface and the orange line is the natural surface. Assume Stations 0+00 and 5+00 are the tie points where the design goes to zero on cuts and fills. What is the balance of material? Is there more cut or more fill?
A.73.56 cu yards cut
B.1929.96 cu yards cut
C.126.45 cu yards fill
D.71.48 cu yards cut