Question: In this problem, we will compare six alternative projects using the general concept of benefit cost ratios. . project project project project project project project
In this problem, we will compare six alternative projects using the general concept of benefit cost ratios. .
| project | project | project | project | project | project | project |
| Description | A | B | C | D | E | F |
| P.W OF COST | 8000 | 1000 | 7000 | 2000 | 10000 | 3000 |
| P.W BENIFITS | 7000 | 2000 | 8400 | 3200 |
Which project has the highest B/C ratio?
a. A
b.B
c. C
d. D
e. E
f. F
B) Which project has B/C ratio less than 1?
a. A
b. B
c. C
d. D
e. E
f. F
A) Which project has the lowest PW of cost?
a. A
b. B
c. C
d. D
e. E
f. F
D) Which investment(s) are not desirable?
a. E only
b. F only
c. D only
d. E&F
e. A&E
f. A&F
g. A, E, and F
h. None of these
E) Which project is preferred?
a. A
b. B
c. C
d. D
e. E
f. F