Question: In time/ schedule management, a WBS is: A. Another word for a cost breakdown which includes risk estimates and other scheduling related costs B. A
In time/ schedule management, a WBS is: A. Another word for a cost breakdown which includes risk estimates and other scheduling related costs B. A monitoring and reporting tool for historical information and change control procedures C. A technique used for subdividing human resources D. The process of subdividing work deliverables into smaller, more manageable piece