Question: In what order would the jobs be processed using the SPT rule? The SPT sequence is -Select-123456Item 9 - -Select-123456Item 10 - -Select-123456Item 11 -
-
In what order would the jobs be processed using the SPT rule?
The SPT sequence is -Select-123456Item 9 - -Select-123456Item 10 - -Select-123456Item 11 - -Select-123456Item 12 - -Select-123456Item 13 - -Select-123456Item 14 .
Compute the average flow time after each job is completed. Round your answer to the nearest whole number.
Average flow time: minutes
Compare this answer with your answer to part a.
The -Select-SPT rulenumerical orderItem 16 minimizes flow time and gets the most work done in the least amount of time.
The following six jobs are to be scheduled on a single machine:
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Processing time (min.) | 130 | 100 | 190 | 60 | 150 | 90 |
Step by Step Solution
There are 3 Steps involved in it