Question: In what project delivery method do architects, engineers, project managers, clients, and contractors sign a joint contract that outlines shared risk and involvement across the
In what project delivery method do architects, engineers, project managers, clients, and contractors sign a joint contract that outlines shared risk and involvement across the entire design and construction process?
DesignBuild
Construction Manager at Risk
DesignBidBuild
Correct!
Integrated Project Delivery
None of the Above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock