Question: In ____, when several activities need the same limited resource at the same time, the activities with the least slack have first priority. a. resource
In ____, when several activities need the same limited resource at the same time, the activities with the least slack have first priority.
a. resource monitoring b. resource limited scheduling c. resource evaluation scheduling d. resource leveling