Question: In your role as project manager you are tasked with evaluating potential suppliers of software packages and systems. Explain the advantages and disadvantages of relying
- In your role as project manager you are tasked with evaluating potential suppliers of software packages and systems. Explain the advantages and disadvantages of relying on a supplier having ISO9001 accreditation as an indicator of quality
- An entrepreneur would like to introduce a new toy in the market. The activities are given as follows.
| Activity | Preceding Activity | Duration in Weeks |
| A | 5 | |
| B | A | 2 |
| C | A | 5 |
| D | B,C | 5 |
| E | D | 5 |
| F | E | 5 |
| G | F | 10 |
| H | B | 10 |
Required
i. Construct the appropriate network diagram
ii. Identify the critical path of the project
iii. What is the expected completion time for the project
- Identify constraints to team development and suggest possible ways of overcoming these constraints. Use relevant examples to support your answer
- A range of software packages can be described as Project management software. What is project management software and what does it do