Question: In your role as project manager you are tasked with evaluating potential suppliers of software packages and systems. Explain the advantages and disadvantages of relying

  1. In your role as project manager you are tasked with evaluating potential suppliers of software packages and systems. Explain the advantages and disadvantages of relying on a supplier having ISO9001 accreditation as an indicator of quality
  2. An entrepreneur would like to introduce a new toy in the market. The activities are given as follows.

Activity

Preceding Activity

Duration in Weeks

A

5

B

A

2

C

A

5

D

B,C

5

E

D

5

F

E

5

G

F

10

H

B

10

Required

i. Construct the appropriate network diagram

ii. Identify the critical path of the project

iii. What is the expected completion time for the project

  1. Identify constraints to team development and suggest possible ways of overcoming these constraints. Use relevant examples to support your answer
  2. A range of software packages can be described as Project management software. What is project management software and what does it do

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!