Question: , Inc., is using acosts-of-quality approach to evaluate design engineering efforts for a new skateboard. Sherrisenior managers expect the engineering work to reduceappraisal, internalfailure, and

, Inc., is using acosts-of-quality approach to evaluate design engineering efforts for a new skateboard. Sherrisenior managers expect the engineering work to reduceappraisal, internalfailure, and external failure activities. The predicted reductions in activities over the2-year life of the skateboards follow. Also shown are the cost allocation rates for each activity. LOADING... (Click the icon to view theinformation.) DATA TABLE
Predicted ActivityCost
Reductionin AllocationRate
Activity ActivityUnits PerUnit
Inspectionofincomingmaterials 395 $45
Inspectionoffinishedgoods 395 19
Numberofdefectiveunits
discoveredin-house 1,400 56
Numberofdefectiveunits
discoveredbycustomers 300 69
Lostsalestodissatisfiedcustomers 125

98

1. Calculate the predicted quality cost savings from the design engineering work.
2. Sherrispent $105,000 on design engineering for the new skateboard. What is the net benefit of this"preventive" qualityactivity?
3.

What major difficulty would Sherri's managers have in implementing thiscosts-of-quality approach? What alternative approach could they use to measure qualityimprovement?

Requirement 1. Calculate the predicted quality cost savings from the design engineering work. The predictive quality cost savings from the design engineering work is $nothing. Requirement 2. Sherri spent $105,000 on design engineering for the new skateboard. What is the net benefit of this"preventive" qualityactivity? The net benefit of the"preventive" quality activity is $nothing. Requirement 3. What major difficulty would Sherri's managers have in implementing thiscosts-of-quality approach? . What alternative approach could they use to measure qualityimprovement? Focus only on financial measures of quality. Monitor competitors' measures of quality and continuously try to improve them. Monitor nonfinancial measures of quality and continuously try to improve them. Enter your answer in each of the answer boxes.
1.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!