Question: In-Class Assignment-14: Case Study: Consider the following project activities: DURATION ACTIVITY (WEEKS) PREDECESSORS B (OCDEE None 6 None None 4 B 6 AB C.
In-Class Assignment-14: Case Study: Consider the following project activities: DURATION ACTIVITY (WEEKS) PREDECESSORS B (OCDEE None 6 None None 4 B 6 AB C. D (a)Draw the network diagram. (b) Calculate the ES, EF, LS, LF, and Slack for each activity. Instructions Early Early Task Time Start Finish Late Start Late Critical Finish Slack A B C D E F (c) What is project completion time?