Question: Including a work breakdown structure or WBS in you project planning usually includes which of the following elements: All of these above are typically included
Including a "work breakdown structure" or WBS in you project planning usually includes which of the following elements:
All of these above are typically included on a WBS
Estimating how long each task will take to complete
Assigning "owners" who are accountable for each task
Identifying the tasks necessary for goal completion