Question: Incorporating sustainability measures into the work breakdown structure during the development of the management plan allows the CM to A ) assign risk probability to

Incorporating sustainability measures into the work breakdown structure during the development of the management plan allows the CM to
A) assign risk probability to sustainability measures.
B) assess the impact of sustainability strategies on project quality.
C) procure appropriate trade contractors.
D) track the progress and costs of the owners sustainability goals.