Question: Indiana Co. began a construction project in 2011 that will provide it $150 million when it is completed in 2013. During 2011, Indiana incurred $36
Indiana Co. began a construction project in 2011 that will provide it $150 million when it is completed in
2013. During 2011, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to
complete the project.
In 2012, Indiana incurred costs of $58.5 million and estimated an additional $40.5 million in costs to
complete the project. Using the percentage-of-completion method, Indiana recognized _______ on the
project in 2012.
A. $15 million gross profit
B. $6 million gross profit
C. $13.5 million gross profit
D. $1.5 million gross profit