Question: Indicate the correct: 1) Net Requirements 2) Planned-Order Receipts 3) Planned- Order Releases Lead time is 1 Week. Note: Leave no cells blank - be
In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Note: Leave no cells blank - be certain to enter " 0 " wherever required