Question: Indirect cost for a project is $ 2 5 0 0 per day. Given the following information, determine an optimum crashing plan. A ) Whatisthecriticalpath?

Indirect cost for a project is $2500 per day. Given the following information, determine an optimum crashing plan. A) Whatisthecriticalpath? B) What is the total cost for the plan? Activity Immediate Normal Crashing potential Crash Cost per day Predecessor(s) Duration (days) A -711000 B A 3--2000 C A 411200 D B, C 511500 E D 211000 F D 421600 G E, F 513000 Use the below chart to complete your answer: (Length After Crashing) Path Initial Duration Activity crashed: Cost to crash ($000): Cumulative cost ($000)