Question: Indirect cost for a project is $ 2 5 0 0 per day. Given the following information, determine an optimum crashing plan. A ) Whatisthecriticalpath?
Indirect cost for a project is $ per day. Given the following information, determine an optimum crashing plan. A Whatisthecriticalpath? B What is the total cost for the plan? Activity Immediate Normal Crashing potential Crash Cost per day Predecessors Duration days A B A C A D B C E D F D G E F Use the below chart to complete your answer: Length After Crashing Path Initial Duration Activity crashed: Cost to crash $: Cumulative cost $