Question: Indirect cost for a project is $ 2 5 0 0 per day. Given the following information, determine an optimum crashing plan. What is the
Indirect cost for a project is $ per day. Given the following information, determine an optimum crashing plan. What is the total cost for the plan?
Activity Immediate
Predecessors Normal Duration days Crashing potential Crash Cost per day
A
B A
C A
D B C
E D
F D
G E F