Question: Indirect cost for a project is $ 2 5 0 0 per day. Given the following information, determine an optimum crashing plan. What is the

Indirect cost for a project is $2500 per day. Given the following information, determine an optimum crashing plan. What is the total cost for the plan?
Activity Immediate
Predecessor(s) Normal Duration (days) Crashing potential Crash Cost per day
A -711000
B A 3--2000
C A 411200
D B, C 511500
E D 211000
F D 421600
G E, F 513000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!