Question: Indirect Cost is 7,000 Php Activity Cost Per Day to Normal Time Crash Time Crash A 6 5 6,900.00 B 8 6 6,000.00 C 7

Indirect Cost is 7,000 Php Activity Cost Per Day

Indirect Cost is 7,000 Php Activity Cost Per Day to Normal Time Crash Time Crash A 6 5 6,900.00 B 8 6 6,000.00 C 7 5 LO 6,000.00 D 12 8 6,000.00 E 7 4 6,000.00 F 3 1 6,000.00 A is the starting activity B and D follows A and precedes F C cannot start until A is finished E follows C and precedes F Fis an ending activity How many days can the project be crashed