Question: Individual Assignment # 2 (Production Planning, Capacity & Bottleneck Analysis) (You may use Excel for your own work, but please submit your answer in PDF
Individual Assignment # 2 (Production Planning, Capacity & Bottleneck Analysis)
(You may use Excel for your own work, but please submit your answer in PDF or Word format)
Purpose:
This assignment is designed to reflect upon several related concepts of Operations Management, such as Production Planning, Bottleneck Management, Capacity and Demand Management, and Sensitivity (What-If) Analysis. This is also a good lead-off to the book, The Goal. You do not need to use Solver in this assignment (though you can).
Task:
You manage the production process in the high-tech facility of Dale Computers Inc. The facility consists of three different assembly lines (1, 2, 3) making two different products, X and Y. Assembly Line 2 is dedicated to the assembly of product X, and assembly line 3 is dedicated to product Y. Assembly Line 1 can assemble both the products. The production process begins with the procurement of raw materials from suppliers. Next, the raw materials are processed into six independent subassemblies, A-F, in separate work areas within the facility. Each product is then assembled from these subassemblies in one of the assembly lines. Product X involves the assembly of subassemblies A, B, C, and E. Product Y requires that subassemblies B, C, D, E, and F be assembled. Subsequent to assembly, each product is finished, customized (painted and other options added), packaged and shipped. Current trends indicate that 20% of product X and 50% of product Y are customized.
Following are the capacities of the work areas producing the subassemblies:
| Subassembly Type | Capacity (Units/Week) |
A | 2450 |
B | 2280 |
C | 2400 |
D | 2450 |
E | 3500 |
F | 1200 |
The annual demands for the products are as shown below:
Product | Sub-assemblies required for one unit of product | Annual Unit Sales |
X | (2 of A); (1 of B, C, E) | 52,000 |
Y | (1 of B, C, F); (2 of D, E) | 52,000 |
The capacities of the assembly lines and the finishing, packaging and customizing areas are as given below:
Assembly line 1 1200 units/week Finishing 2500 units/week
Assembly line 2 500 units/week Customizing 850 units/week
Assembly line 3 600 units/week Packaging 3000 units/week
Notes: (1) Assume 52 operating weeks/year. Converting to weekly demand may be helpful.
(2) Plan production to just meet the demand (do not overproduce).
Answer the following questions Show your calculations.
- From the point of view of capacity management, what is the key business issue for Dale Computers, given that demand forecast is available? [Note: Answer this in concept, before you do Part 2 below] (10%)
- With the current weekly demands of 1000 for each product X and Y, what is the current bottleneck resource? Show your calculations. [Note: Don't change demand yet] (50%)
- Management must deal with changing demand and resource constraint, by analyzing alternative business scenarios. If the weekly demand for X and Y increased proportionately (= by same percentage), identify the top three resources that are bottleneck candidates. Show your calculations. [Note: Take Assembly Lines together as a single resource] (20%)
- Now, if demands for X and Y change disproportionately (= by different percentage) in the above situation, what does your analysis tell you about its effect on bottleneck shift, especially in product mix situation of a multiple product plant? Defend your answer with necessary "what-if" examples. [Note: this part will assess your critical thinking] (20%)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts