Question: Individual Project: Earned Value Management Please answer the following questions, and please show your work process. Providing answers only will not receive a 0 grade.

Individual Project: Earned Value Management Please answer the following questions, and please show your work process. Providing answers only will not receive a 0 grade. To complete this project, you need to study the module materials well and do some research. 1. At a weekly meeting during the project implementation, the project manager Charlie used the following table to inform everyone of the current progress. According to this table, find the current progress of the project. (20 points) 2. For a project in progress, the current PV=$2200,EV=$2000,AC=$2500, find the current project's SV and project status \& CPI and cost performance. (20 points)