Question: Information for Machine Shop 1 table [ [ , table [ [ Machine ] , [ Shop 1 ] ] ] , [

Information for Machine Shop 1
\table[[,\table[[Machine],[Shop 1]]],[\table[[Demand (from Machine Shop 2) units per],[day]],36,750],[\table[[Average lead time for replenishment of],[one container per hour]],0.12],[Safety factor,0.15],[Container size,300],[Working hours per day,8]]
N=DT(1+x)C
where
N= Total number of kanbans (one kanban per container)
D= Average usage rate of using work centre
T= Average lead time for replenishment of one container (include production, setup, production, and transport times)
x= Saferv factor usuallv given as a nercentage of average ucage D
 Information for Machine Shop 1 \table[[,\table[[Machine],[Shop 1]]],[\table[[Demand (from Machine Shop 2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!