Question: Information for the Time-Cost Model Exercise Crash Immediate Normal Time Task Time Predecessors (weeks) (weeks) NONE 2 1 Normal Cost Crash Cost B A 3
Information for the Time-Cost Model Exercise Crash Immediate Normal Time Task Time Predecessors (weeks) (weeks) NONE 2 1 Normal Cost Crash Cost B A 3 1 A 4 4 D 5 4 $5,000 $13,000 $10,000 $20,000 $6,000 $6,000 $4,000 $8,000 $4,000 $9,000 $5,000 $9,000 $3,000 $6,000 E B&C 6 4 F 3 2 D&E F G 2 2 1 Your firm is creating new marketing material for an existing product in order to increase customer demand. The table below lists the steps that need to be complete. You recently found out if he project isn't complete by the end of the year this product will have to be discontinued. How long will the project take to complete it you only have $10,000 to spend on crashing? 13 15 12 14
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
