Question: Information for the Time-Cost Model Exercise Normal Crash Normal Task Immediate Cost Crash Time Time Predecessors Cost (weeks) (weeks) A NONE 8 6 $5,000 $13,000

Information for the Time-Cost Model Exercise Normal Crash Normal Task Immediate Cost Crash Time Time Predecessors Cost (weeks) (weeks) A NONE 8 6 $5,000 $13,000 B A 12 10 $10,000 $20,000 C A 15 15 $6,000 $6,000 D C 17 13 $4,000 $8,000 B & C 18 16 $4,000 $9,000 7 m D & E 9 7 $5,000 $9,000 F 8 7 $3,000 $6,000 Your firm is launching a new product to the market. The table lists the steps that need to be complete to get the product to market. You have recently found out that a competitor is launching a similar product and you need to get to market first. How long will the project take to complete if you only have $10,000 to spend on crashing? 51 55 54 53