Question: information immediate and long - term deflections for the example presented in Tutorial 2 ( Tutorial 2 other applied loads. Tutorial 2 Background This example

information immediate and long-term deflections for the example presented in Tutorial 2(Tutorial 2
other applied loads.
Tutorial 2
Background
This example is based on concrete bridge girders that were
designed, casted and tested up to failure as part of a linkage
project with the precast industry to study the economic and practical constraints of short production turnaround times, and
the competitiveness against steel girders. A solution was
and stiffness when releasing tensioning strands at an early age.
Tutorial 2
Background
The active reinforcement was composed of twelve 38-in prestressing bonded strands at the bottom and two 3/8-in strands were initially strands at the top. The pretensioning strands were initially stretched to 1,446MPa before the concrete was poured and were kept attached to the precast table until day 5. At day 5, the transfer took place and the post-tensioning strands were stretched to 1,100 MPc.
The post-tensioning strands were only installed to avoid premature failure due to the high level of stress applied by the pretensioning strands at such an early age. Once the girders are finally taken to a construction site to erect a bridge, the post-tensioning strands are meant to be deal enough vertical load is applied to the structure.
Tutorial 2
Geometry
Tutorial 2
Tutorial 2
Calcul
information immediate and long - term deflections

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!