Information on Marigold's direct labor costs for the month of August is as follows:
Actual rate | $6 |
Standard hours | 11000 |
Actual hours | 10000 |
Direct labor price varianceāunfavorable | $4800 |
What was the standard rate for August?
$5.95
$6.05
$5.52
$6.48