Question: Initial outlay After one year After two years After three years '000 (400) 40 300 300 What will be the NPV (net present value)

Initial outlay After one year After two years After three years '000

Initial outlay After one year After two years After three years '000 (400) 40 300 300 What will be the NPV (net present value) of this project if a discount rate of 15% is used? +60.8k -60.8k +240k +460.8k