Initially, Project Janji Manismu Menghiris Kalbu is estimated to complete within SEVEN (7) months. However, seven...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Initially, Project "Janji Manismu Menghiris Kalbu" is estimated to complete within SEVEN (7) months. However, seven months have passed, and the project is yet to be completed. Based on the earned value in Table 1.0 below, answer the following questions: Month Jan Feb Mar Apr May Activity (RM) (RM) (RM) (RM) (RM) June July (RM) (RM) Budget at Completion % Complete (RM) A 750 320 1,070 100 B 400 225 150 775 100 C 1,800 780 550 3,130 100 D 400 2600 3,300 350 6,650 95 E 680 400 390 1,470 75 F 640 125 875 1,640 45 Monthly Planned 750 720 2,425 3,530 5,170 875 1,265 Cost Monthly Actual 720 660 2,200 3,400 4,800 780 1,000 Cost Table 1.0: Project "Janji Manismu Menghiris Kalbu" a) b) c) Table 1.0: Project "Janji Manismu Menghiris Kalbu" Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places). (25 Marks) Identify the new Estimated Cost to Completion for the project (round your answers into TWO (2) decimal places). (4 Marks) Based on the calculated Schedule Performance Index (SPI) how do you conclude the performance of your project team? (1 Mark) [Total: 30 Marks] Initially, Project "Janji Manismu Menghiris Kalbu" is estimated to complete within SEVEN (7) months. However, seven months have passed, and the project is yet to be completed. Based on the earned value in Table 1.0 below, answer the following questions: Month Jan Feb Mar Apr May Activity (RM) (RM) (RM) (RM) (RM) June July (RM) (RM) Budget at Completion % Complete (RM) A 750 320 1,070 100 B 400 225 150 775 100 C 1,800 780 550 3,130 100 D 400 2600 3,300 350 6,650 95 E 680 400 390 1,470 75 F 640 125 875 1,640 45 Monthly Planned 750 720 2,425 3,530 5,170 875 1,265 Cost Monthly Actual 720 660 2,200 3,400 4,800 780 1,000 Cost Table 1.0: Project "Janji Manismu Menghiris Kalbu" a) b) c) Table 1.0: Project "Janji Manismu Menghiris Kalbu" Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places). (25 Marks) Identify the new Estimated Cost to Completion for the project (round your answers into TWO (2) decimal places). (4 Marks) Based on the calculated Schedule Performance Index (SPI) how do you conclude the performance of your project team? (1 Mark) [Total: 30 Marks]
Expert Answer:
Answer rating: 100% (QA)
To determine the new Estimated Time to Completion ETC and Estimated Cost to Completion ECC we can use the Earned Value Analysis formulas Lets calculat... View the full answer
Related Book For
Project Management in Practice
ISBN: 978-0470533017
4th edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
Posted Date:
Students also viewed these finance questions
-
5) On the graphs below show the difference between a change in price and a change in demand. Fully label graphs for full marks! (2+2 marks) Change in price Change in demand X 6) A change in the price...
-
The MidLands Trucking Company based in Louisville has eight trucks located throughout the Mideast that have delivered their loads and are available for shipments. Through their Internet logistics...
-
On March 1, 2018, Brown-Ferring Corporation issued $100 million of 12% bonds, dated January 1, 2018, for $99 million (plus accrued interest). The bonds mature on December 31, 2037, and pay interest...
-
Felix and Sam are roommates. They both want the dishes to be washed, but each would prefer that the other person do it. Use the decision matrix in Figure 9Q-1 to explain why Felix and Sam are likely...
-
Make decisions in the situations described in the Ethical Behavior Worksheet. You will not have all the background information on each situation; instead, you should make whatever assumptions you...
-
Jannero Pargo opened Pargos Cleaning Service on July 1, 2012. During July the following transactions were completed. July 1 Pargo invested $20,000 cash in the business. 1 Purchased used truck for...
-
4. Consider the tables of values for the two functions shown. x y = f(x) -2 5 y = g(x) -2 -1 6 -1 0 8 1 1 7 0 2 9 2 Complete the table of values for the composite function y = f(g(x)). - x y =...
-
A single wire of length L = 2.5 m is parallel to a ground plane and 10 cm above it. The wire carries a sinusoidal current with amplitude I1 = 17 mA at the frequency f = 400 MHz. An antenna is...
-
Scenario planning is about... Preparing only for those scenarios that are both impactful and uncertain. Identifying scenarios that are most likely to happen. Preparing for scenarios that are...
-
Find the velocity of the masses just before me hits the floor. g=10m/s msky 0=37* K-05 my loving 15M
-
Discuss creative destruction . Provide at least 1 example?
-
When there is an increase in aggregate demand, firms need to produce more goods and services, leading to an increase in the demand for labor. This is represented by a rightward shift of the labor...
-
Leave m fixed at the zero mark the whole time. Move m to the 7.0 metre mark. Observe the size and direction of both force arrows shown in the simulation. Now, still leaving m at the zero mark, move m...
-
The transactions completed by PS Music during June 2018 were described at the end of Chapter 1. The following transactions were completed during July, the second month of the businesss operations:...
-
An Atomic Energy Commission nuclear facility was established in Hanford, Washington, in 1943. Over the years, a significant amount of strontium 90 and cesium 137 leaked into the Columbia River. In a...
-
Aside from the obvious benefits for project control, what other benefits might result from a good project reporting system?
-
What purpose(s) might be served by using each of the following priority rules for allocating scarce resources? a. As late as possible b. Shortest task duration time first c. Minimum slack first
-
What should Avery Mitchell do next? What information should he ask the consultants for before accepting their proposal? What project planning tools would you suggest Avery ask the consultants to use...
-
Last year, Miley decided to terminate the S corporation election of her solely owned corporation on October 17, 2018 (effective immediately), in preparation for taking it public. At the time of the...
-
You have been assigned to compute the income tax provision for Motown Memories Inc. (MM) as of December 31, 2019. The companys income statement for 2019 is provided below: MM prepared the following...
-
Jane has been operating Mansfield Park as a C corporation and decides she would like to make an S election. What is the earliest the election will become effective under each of these alternative...
Study smarter with the SolutionInn App