Question: Insert the numbers and headings in your table as seen in the example file. Do not re-create the box art with arrows. That is only
Insert the numbers and headings in your table as seen in the example file. Do not re-create the box art with arrows. That is only for your information to help see the project's flow. Complete the expected times and their variance, the earliest start & finish and latest start & finish times, and the budget numbers for the earliest start scenario.

Project Management Assignment Complete Highlighted Cells ACTIVITY EARLIEST EARLIEST LATEST LATEST BUDGETED BUDGETED START FINISH START FINISH SLACK COST/WEEK TOTAL COST A 11000 B 13000 C 12000 D 10000 E 11000 15000 G 9000 H 10000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
