Question: Instruction: Given the table below, complete the missing cell values applying the Exponential Smoothing method of forecasting and Mean Absolute Deviation. Answer also the other
Instruction: Given the table below, complete the missing cell values applying the Exponential Smoothing method of forecasting and Mean Absolute Deviation. Answer also the other 3 related questions below the table. Numbers with decimals should take 2 decimal places. (.2 mark for each box or question)
| Quarter | Actual Tonnage Unloaded | Forecast for = .2 | Absolute Deviation for = .2 | Forecast for = .5 | Absolute Deviation for = .5 |
| 1 | 180 | 175 | 5.00 | 175 | 5.00 |
| 2 | 180 | 2.50 | |||
| 3 | 185 | 176.8 | 8.20 | 178.8 | 6.25 |
| 4 | 170 | 178.4 | 8.44 | 181.9 | 11.88 |
| 5 | 180 | 176.8 | 3.25 | 175.9 | 4.06 |
| 6 | 190 | 177.4 | 12.60 | 178.0 | 12.03 |
| 7 | 170 | 179.9 | 9.92 | 184.0 | 13.98 |
| 8 | 185 | 177.9 | 7.06 | 177.0 | 8.01 |
| Sum of absolute deviation = |
Additional questions:
1.
What is the MAD for = .2?
Your answer:
Computation/solution:
Your final computed value:
2.
What is the MAD for = .5?
Your answer:
Computation/solution:
Your final computed value:
3.
Which smoothing constant would you prefer?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts