Question: Instruction: Given the table below, complete the missing cell values applying the Exponential Smoothing method of forecasting and Mean Absolute Deviation. Answer also the other

Instruction: Given the table below, complete the missing cell values applying the Exponential Smoothing method of forecasting and Mean Absolute Deviation. Answer also the other 3 related questions below the table. Numbers with decimals should take 2 decimal places. (.2 mark for each box or question)

Quarter Actual Tonnage Unloaded

Forecast for

= .2

Absolute Deviation

for = .2

Forecast for

= .5

Absolute Deviation

for = .5

1 180 175 5.00 175 5.00
2 180 2.50
3 185 176.8 8.20 178.8 6.25
4 170 178.4 8.44 181.9 11.88
5 180 176.8 3.25 175.9 4.06
6 190 177.4 12.60 178.0 12.03
7 170 179.9 9.92 184.0 13.98
8 185 177.9 7.06 177.0 8.01
Sum of absolute deviation =

Additional questions:

1.

What is the MAD for = .2?

Your answer:

Computation/solution:

Your final computed value:

2.

What is the MAD for = .5?

Your answer:

Computation/solution:

Your final computed value:

3.

Which smoothing constant would you prefer?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!