Question: Instruction. Project CE is a Utilities Installation Project. Wherein we will install water pipes, sewer pipes and electrical wirings underground. Given the information below, answer
Instruction. Project CE is a Utilities Installation Project. Wherein we will install water pipes, sewer pipes and electrical wirings underground. Given the information below, answer the following questions;
tableActivityDescription,PredecessolIDDescription,tableDurationDaysASite Clearing,NoneBSurveying and layout.,tableCannot start before the site is cleared; otherwise, many of thesurvey stakes would be lost in the clearing operationcRough Grading,Cannot start until the area has been survey and laid out.,DDrilling of well,Cannot start until the rough grading operation is completed.,EtableInstallation of wellpumpCannot be done until well is completed drilled.,FtableUnderground water pipingtableAlthough this might be started earlier, the site contractorprefers to work starting from the pump toward the buildingsiteGtableInstallation of Watertank foundationtableAfter the rough grading, these simple foundations can beinstalledHErection of water tank,tableThe water tank cannot be erected until the foundations arepouredItableTank piping andvalvestableCannot be fabricated and installed until the water tank iscompletedJtableConnecting all thewater pipes & valvestableThe water piping cannot be linked up until both sections tankpiping & valves are completed.KExcavation for sewer,Can be started after rough grading.,LtableInstallation of thesewer and backfillImmediately follows after sewer excavation.,MtableExcavation forelectrical manholesCan start after rough grading.,NtableInstallation ofelectrical manholesCannot start until the excavation for manholes is completed.,tableInstallation ofelectrical duct banktableStart after the electrical manholes are complete and thecompletion of the sewer line, because that line is deeper thanthe duct bank.PtableInstallation ofoverhead pole lineCan be started after the site is rough graded.,QtablePulling of the powerfeeder electrictableCan start after both the duct bank and the overhead pole lineare installed and ready to receive the cableRtableDrafting of BuildingLayouttableIt is dependent on the completion of the installation of allelectric and water lines pipes & valves
Identify the Critical Path, Duration, ESEFLSLF TF FF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
