Question: Instruction. Project CE is a Utilities Installation Project. Wherein we will install water pipes, sewer pipes and electrical wirings underground. Given the information below, answer

Instruction. Project CE is a Utilities Installation Project. Wherein we will install water pipes, sewer pipes and electrical wirings underground. Given the information below, answer the following questions;
\table[[Activity,Description,Predecessol],[ID,Description,\table[[Duration],[(Days)]]],[A,Site Clearing,3,-,None],[B,Surveying and layout.,2,\table[[Cannot start before the site is cleared; otherwise, many of the],[survey stakes would be lost in the clearing operation]],],[c,Rough Grading,2,Cannot start until the area has been survey and laid out.,],[D,Drilling of well,15,Cannot start until the rough grading operation is completed.,],[E,\table[[Installation of well],[pump]],2,Cannot be done until well is completed drilled.,],[F,\table[[Underground water],[, piping]],8,\table[[Although this might be started earlier, the site contractor],[prefers to work starting from the pump toward the building],[site.]],],[G,\table[[Installation of Water],[tank foundation]],4,\table[[After the rough grading, these simple foundations can be],[installed.]],],[H,Erection of water tank,10,\table[[The water tank cannot be erected until the foundations are],[poured.]],],[I,\table[[Tank piping and],[valves]],10,\table[[Cannot be fabricated and installed until the water tank is],[completed.]],],[J,\table[[Connecting all the],[water pipes & valves]],2,\table[[The water piping cannot be linked up until both sections (tank],[piping & valves) are completed.]],],[K,Excavation for sewer,10,Can be started after rough grading.,],[L,\table[[Installation of the],[sewer and backfill]],5,Immediately follows after sewer excavation.,],[M,\table[[Excavation for],[electrical manholes]],1,Can start after rough grading.,],[N,\table[[Installation of],[electrical manholes]],5,Cannot start until the excavation for manholes is completed.,],[0,\table[[Installation of],[electrical duct bank]],3,\table[[Start after the electrical manholes are complete and the],[completion of the sewer line, because that line is deeper than],[the duct bank.]],],[P,\table[[Installation of],[overhead pole line]],6,Can be started after the site is rough graded.,],[Q,\table[[Pulling of the power],[feeder (electric)]],5,\table[[Can start after both the duct bank and the overhead pole line],[are installed and ready to receive the cable]],],[R,\table[[Drafting of Building],[Layout]],1,\table[[It is dependent on the completion of the installation of all],[electric and water lines (pipes & valves).]],]]
Identify the Critical Path, Duration, ES,EF,LS,LF, TF, FF
Instruction. Project CE is a Utilities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!