Question: Instructions for Problem 4: PERT Cost (10 Points) Based on the information below, prepare a comprehensive report that includes the following: The complete budget using
Instructions for Problem 4: PERT Cost (10 Points)
Based on the information below, prepare a comprehensive report that includes the following:
- The complete budget using ES times.
- Suppose the project is on its 10th week. Using this information, determine if the project is on track given that:
- Activity A is 100% done with a cost of $1,800
- Activity B is 100% done with a cost of $6,000
- Activity C is 80% done with a cost of $6,000
- Activity D is 100% done with a cost of $8,500
- Activities E and F have not been started
- Prepare a short report on the writing of the project including a recommended strategy on the next steps.
Problem 4: PERT Cost (10 Points)
A project requires these activities to be completed and the table below shows the expected time and budgeted cost for each activity.
| Activity | Expected time (weeks) | Budgeted Cost | Immediate Predecessors |
| A | 3 | $2,000 | None |
| B | 4 | $6,000 | None |
| C | 2 | $7,000 | A |
| D | 5 | $9,000 | B |
| E | 3 | $3,000 | C |
| F | 6 | $8,000 | B, D |
Step by Step Solution
There are 3 Steps involved in it