Question: Instructions For the Project data shown below, conduct a project management analysis: 1. Construct the network diagram, (Earliest Start and Earliest Finish, Latest Start

Instructions For the Project data shown below, conduct a project management analysis:

Instructions For the Project data shown below, conduct a project management analysis: 1. Construct the network diagram, (Earliest Start and Earliest Finish, Latest Start and Latest Finish). 2. Identify the slack Time for each activity. 3. Identify the Critical Path, and how long does it take to complete the project? Activity ID D Duration 7 3 Dependency B C 6 A D 3 B E 3 D,F F 2 G 3 B C H 2 E,G