Question: Instructions: Read and complete the attached assignment. Submit the completed assignment using Word (.doc) or Excel (.xls) documents. Answer all questions and show calculations for
Instructions:
- Read and complete the attached assignment.
- Submit the completed assignment using Word (.doc) or Excel (.xls) documents.
- Answer all questions and show calculations for the work.
- Check the Rubric
Situation: A firm has a capital budget of $100, which must be spent on one of two projects, each requiring a present outlay of $100. Project A yields a return of $120 after one year, whereas Project B yields $201.14 after 5 years.
Questions:
- What is the NPV of each project using a discount rate of 10%?
- What is the IRR of each project?
- What are the project rankings based on these two investment decision rules?