Question: INSTRUCTIONS: Submit a work, excel, and / or PDF document that addresses the following questions and actions. An activity - on - node precedence diagram

INSTRUCTIONS: Submit a work, excel, and/or PDF document that addresses the following questions and actions.
An activity-on-node precedence diagram is shown below. The labor resources for each activity are shown within the diagram. If there are a maximum of 8 laborers available for the project, calculate the following:
Build a resource-loaded schedule (bar chart format).
The total project duration without considering the resource constraint is:
Which days exceed the 8 laborer constraint?
The minimum total project duration considering the 8 laborer constraint for each day is:
Assuming Activity A,B, and C , has no labor constraint per day (i.e. it is not necessary for all the laborers to work the same day, however, the total amount of work is still the same). Is there a way project can finish on time, without extending it? If yes, how?
please do it urgently.
please follow strictly instructions
INSTRUCTIONS: Submit a work, excel, and / or PDF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!