Question: INSTRUCTIONS: Submit a work, excel, and / or PDF document that addresses the following questions and actions. An activity - on - node precedence diagram
INSTRUCTIONS: Submit a work, excel, andor PDF document that addresses the following questions and actions.
An activityonnode precedence diagram is shown below. The labor resources for each activity are shown within the diagram. If there are a maximum of laborers available for the project, calculate the following:
Build a resourceloaded schedule bar chart format
The total project duration without considering the resource constraint is:
Which days exceed the laborer constraint?
The minimum total project duration considering the laborer constraint for each day is:
Assuming Activity and C has no labor constraint per day ie it is not necessary for all the laborers to work the same day, however, the total amount of work is still the same Is there a way project can finish on time, without extending it If yes, how?
please do it urgently.
please follow strictly instructions
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock