Question: Instructions: - Submit your work as a Word file. Only Word files will be accepted for grading! Use the file name HW 8 for the
Instructions:
Submit your work as a Word file. Only Word files will be accepted for grading! Use the file name HW for the file you submit.
Give a separate solution for each part of the assignment and include your explanations for the associated logic.
Do not use Microsoft Project or similar project planning software for this assignment.
Assigned Work:
A certain project is defined by the data given in the following table:
a Based on that data, draw in Word, a fully analyzed network diagram for the project. Include all activity times in your network diagram. Identify the critical path and determine the project duration. Finally, prepare an Activities Boundary Timetable for the project. Alternatively you may use another software to draw the network diagram and copy and paste the diagram into Word. Make sure the diagram is legible in Word. Scanned manual drawings, handdrawn diagrams from a tablet or similar device, and diagrams generated by MSP or similar project planning software are not acceptable for grading. points
b Assuming that each task is started as soon as possible, construct the Gantt chart and corresponding resource loading diagram for the project. While not required, it may be convenient to do this in a spreadsheet program such as Excel, and then copy and paste your work into Word. points
c How would you rearrange the timing of project activities to reduce the fluctuation in resource demand? Assume that the overall project duration cannot be extended. Remember that the specified precedence relationships must be maintained. points
d If there are only workers available for the project, how would you assign workers to tasks to ensure that the project can be completed without violating the resource limit In this case, the project duration may be extended if necessary but without violating precedence relationships points
e Given the results from c and d above, what recommendations would you make to senior management regarding the staffing of this project, and why? points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock